Calcutta Electric Supply Corporation Vs. Sh. N.M. Banka & Anr.
(Arising out of S.L.P.(C) No.4208 of 1992 )
(From the Judgment and Order dated 11.02.92 of the Calcutta High Court in Appeal No.Nil/91.)
(Arising out of S.L.P.(C) No.4208 of 1992 )
(From the Judgment and Order dated 11.02.92 of the Calcutta High Court in Appeal No.Nil/91.)
Mr. Dr.Shankar Ghosh and Mr. S.B.Sanyal, Senior Advocates, Mr. A.N. Dawn , Mr.Tapash Banerjee, Mr. S.Dutta and Mr.B.K.Satija, Advocates with them for the Respondents.
Section 26 (4) – Defaulter not having paid huge electricity bills got a second electricity connection in name of partner without disclosing correct facts – Writ – Held that this is a case of gross abuse of process of Court – Writ continued to linger for five years and defaulter allowed to continue to draw electricity without paying arrears – Without moving under Section 26(4), the statutory remedy, defaulter approached the Court and was allowed – By passing the statutory remedy – Order passed for payment of Rs.30 lakhs with cost and then the dispute to be decided by Chief Electricity Inspector.
Writ;
Fraudulent move and gross abuse of Court and writ jurisdiction – And CESC rightly refused to grant the second line.
The writ petitioners did not avail of the statutory remedy provided by sub-sections (4) and (6) of Section 26 but approached the Court for interim relief and by this process, managed to continue to get supply of electricity even though there was a huge mounting default. It is difficult to understand how the Court allowed the question of these disputed bills to linger on for more than five years without disposing of the case on merits. It was also not proper for the Court to direct CESC to supply electricity to a defaulter indefinitely by interim orders passed from time to time. Specific statutory remedy provided by the Indian Electricity Act to the consumer should not have been allowed to be bypassed.
We fail to see the sense of this prayer. If the consumer was aggrieved by the bills, he should have approached the Electric Inspector straight away. When the consumer approached the Court, the Court should have declined to intervene in the matter and should have directed the consumer to avail of the statutory remedy. In any event, under the writ jurisdiction, the Court could not have decided about the correctness or otherwise of the bills. Serious allegations were made by CESC about the consumption of electricity beyond the sanctioned load and also of non-payment of valid bills. The allegation is also that when the electricity supply to Rajkumar Dyeing & Printing Works was stopped, a partner, Banka, wanted to get a service line in his own name at the same place to run the printing works . This was obviously a fraudulent move and the CESC rightly refused to grant the second line. (Paras 4 & 5)
1. The following order in this case was passed by us on 6th November, 1996.
” While we propose to give reason for our Order later, the following is the operative and final Order in the Special Leave Petition :
Leave granted.
The appeal is allowed with the following directions:
(1) Within one month from today, Respondent No.1- consumer shall deposit a sum of Rupees thirty lakhs towards the demand of arrears by the appellant – company against him.
(2) On such deposit being made, the dispute between the parties involved in the Transferred case No.42 of 1996 shall stand referred to the Chief Electrical Inspector, Calcutta who shall decide the same within two months from the date the dispute is refereed to him.
(3) If the amount specified in Direction No.1 is not deposited, it shall be open to the appellant- company to recover the arrears due to it according to law.
(4) Pending further orders in the matter, all the properties of the respondent are attached herewith.
(5) Respondent No.1 shall pay the costs of the appellant which are estimated at Rupees fifty thousand only.”
2. The reasons for passing the aforesaid order are as under:
This is a case of gross abuse of process of court. One N.M. Banka had applied to CESC Limited which carries on business of generation, supply and distribution of electricity in Calcutta and its suburbs for a connection of electricity to premises No.11 , U.N. Mukherjee Road, Calcutta. After completion of inspection, the CESC agreed to supply electricity to N.M.Banka by letter dated 5th February, 1988 subject to compliance of usual conditions. Some time later, it came to the knowledge of CESC that N.M.Banka was a partner of the firm M/s. Rajkumar Dyeing & Printing Works which was carrying on business at the same premises. The partnership firm was an existing registered consumer from whom a very substantial sum of money was lying due. Moreover, the partnership firm was found drawing electricity far in excess of the sanctioned load of 50 H.P. On coming to know that N.M.Banka was a partner of Rajkumar Dyeing & Printing Works, which was a defaulter in payment of electricity charges, the CESC Limited by letter dated 22 September, 1988 informed Banka that supply of electricity to him has been kept in abeyance. Apart from the huge liability of Rajkumar Dyeing & Printing Works, there was also a technical difficulty in giving a separate electric connection to Banka because it was not possible to give two separate connections to one particular premises. Existence of two services in the same premises would be hazardous.
3. On 22nd July, 1988, a writ petition was moved by Rajkumar Dyeing & Printing Works, the partnership firm and also Shri Banka, the partner for a direction in the nature of mandamus commanding CESC and their officers from disconnecting the electricity line of the factory situated at No.11, U.N.Mukherjee Road, Calcutta. A prayer was also made to refer the disputed bills to the arbitrator as provided in the Indian Electricity Act for adjudication. The allegation was that CESC had issued an inflated bill for the month of June 1988 and were threatening disconnection of electricity to the appellants if they failed to pay the said bill by 20th July, 1988. It was further prayed that if the electricity line was disconnected, the factory will have to be closed down and about 90 workers will have to be laid off without any fault of the appellants. The writ petition was moved exparte and a direction was given that the electricity supply will not be disconnected ’till Wednesday next’. On 28th July, 1988, the matter was once again heard exparte and the interim order not to disconnect the supply was further continued. The matter, thereafter, has come up for hearing from time to time and the interim order has been continued with occasional directions to deposit some money. By this process, the writ petition was kept pending for more than five years. The appellant who was a defaulter when the writ petition was filed continued to get supply of the electricity by making occasional payments pursuant to the direction of the Court. The writ petitioner did not pay the bills submitted in usual course, the arrears kept mounting up and the CESC ultimately disconnected the line . By an order dated 16th February, 1993, the Court directed the line to be restored and the writ petition was directed to remain heard in part.
4. It is difficult to understand how this writ petition was allowed to linger on for five years. The Court did not and could not possibly come to a finding on the disputed question of facts. According to CESC, the bills were prepared properly. The appellants did not pay the bills. The total amount of arrears due to the CESC had mounted up to Rs.67,40,948.10 after giving due credit to the payments made by the appellants pursuant to the interim orders passed by the Court from time to time . On behalf of the CESC, very serious allegations have been made about theft of electricity and overloading as a result of which the meter was burnt out several times and non-payment of bills. Section 24 of the Electricity Act gives the right to the supplier to disconnect any electric supply line after giving seven days’ notice, if a consumer neglects to pay the charge for energy or any sum other than the charge for energy due from him in respect of supply of energy . In case of dispute of difference about the meter or the correctness of the bill, the consumer may apply to the Electrical Inspector. The inspector in such a case shall estimate the amount of energy supplied to the consumer. The supplier shall not be at liberty to take off or remove any meter until the dispute has been determined by the Electrical Inspector. The writ petitioners did not avail of the statutory remedy provided by sub-sections (4) and (6) of Section 26 but approached the Court for interim relief and by this process, managed to continue to get supply of electricity even though there was a huge mounting default. It is difficult to understand how the Court allowed the question of these disputed bills to linger on for more than five years without disposing of the case on merits. It was also not proper for the Court to direct CESC to supply electricity to a defaulter indefinitely by interim orders passed from time to time. Specific statutory remedy provided by the Indian Electricity Act to the consumer should not have been allowed to be bypassed.
5. It has been contended on behalf of the consumer that the second prayer in the writ petition was referring the matter for arbitration. We fail to see the sense of this prayer. If the consumer was aggrieved by the bills, he should have approached the Electric Inspector straight away. When the consumer approached the Court, the Court should have declined to intervene in the matter and should have directed the consumer to avail of the statutory remedy. In any event, under the writ jurisdiction, the Court could not have decided about the correctness or otherwise of the bills. Serious allegations were made by CESC about the consumption of electricity beyond the sanctioned load and also of non-payment of valid bills. The allegation is also that when the electricity supply to Rajkumar Dyeing & Printing Works was stopped, a partner, Banka, wanted to get a service line in his own name at the same place to run the printing works . This was obviously a fraudulent move and the CESC rightly refused to grant the second line.