Army Welfare Housing Organisation Vs. M/s. Gautam Construction & Fisheries Ltd.
( From the Judgment and Order dated 18.9.95 of the Madras High Court in Application Nos. 3092 , 3095 , 3231-32 of 1995 in O.A.No. 630 of 1995 )
( From the Judgment and Order dated 18.9.95 of the Madras High Court in Application Nos. 3092 , 3095 , 3231-32 of 1995 in O.A.No. 630 of 1995 )
Mr. D.D.Thakur , Sr. Advocate , Mr. Ajay Kumar Yadav , Mr. N.N. Bhatt and Mr. K.V.Mohan , Advocates with him for the Respondents
Arbitration Act, 1940
Section 15 ,17 ,33 – Objections – Modification of Award – ” Firm liability ” and ” anticipated expenses ” – Decision of Arbitrator that amount is ” anticipated expenses ” . Held that the Arbitrator having considered all things , there can be no re-appreciation and to hold otherwise .
( Para 5 )
1 . IAs 17 to 20 of 1998 are objections filed by M/s Gautam Construction and Fisheries Ltd.( GC&FL ) under Sections 15 , 17 and 33 of the Arbitration Act , 1940 ( for short , the ‘Act ‘ ) to the award dated September 9 , 1997 of the sole Arbitrator , Justice V. Khalid , a retired Judge of this Court . IAs 21 to 24 are the objections similarly filed by the Army Welfare Housing Organisa-tion ( AWHO ) against the same award .
2 . GC&FL in their objections seek directions for modification of the award to correct an error with regard to wrong deduction of Rs.30 ,000 ,00/- twice by the Arbitrator from their claims 1 and 13 in their statement of claim . They have also claimed interest @ 18% per annum on the amount of the award in their favour till payment . AWHO in their objections also seek modification of the award stating that their claim for anticipated liability towards completion of the contract was wrongly rejected by the Arbitrator when some of the amounts claimed were towards ” firm liability ” . Both parties disputed the objections of each other to the award as aforesaid .
3 . Little background will be necessary to understand the objec-tions raised by the parties . There was a contract entered into between them for construction of certain number of dwelling units by GC&FL for AWHO on the land belonging to GC&FL . Contract con-tained an arbitration clause . Disputes arose between the parties resulting in cancellation of contract by the AWHO and issuance of publication of notice for re-tendering of the contract for the balance of the work . Instead of seeking appointment of arbitra-tor under the terms of the contract , GC&FL filed an application under Section 20 of the Act and also filed an application under Section 41 of the Act seeking interim directions . These proceed-ings were filed in the Madras High Court . The learned single Judge by order dated September 18 , 1995 appointed a retired Judge of the Madras High Court as sole arbitrator and at the same time restrained AWHO from re-tendering the work pending disposal of arbitration proceedings . Arbitration agreement under the con-tract prescribed a different mode for appointment of arbitrator but that is not relevant now and unnecessary for us to examine that aspect . Aggrieved by the judgment of the High Court , AWHO sought leave to appeal to this Court which was granted by order dated December 4 , 1995 and the appeal itself was also heard and disposed of on the same day . With the consent of the parties , this Court then appointed Justice V. Khalid , a retired Judge of this Court , as the Arbitrator and also authorised him to take any help from any technically qualified person . Liberty was given to the parties to approach the Arbitrator for any interim relief including vacation of the injunction order granted by the High Court regarding re-tendering of the work . It was also directed that the Arbitrator would file the award in this Court only and other courts were interdicted from interfering in the arbitration proceedings .
4 . After entering in to the reference , the Arbitrator gave an interim award on May 8 , 1996 whereby he vacated the order of injunction granted by the High Court in its judgment dated Sep-tember 18 , 1995 . This interim award when filed in this Court was made rule of the Court as no party filed any objection to the same . Thereafter , the Arbitrator gave his final award on Septem-ber 9 , 1997 and on notice of filing the same given to the par-ties , they filed their objections now under consideration .
5 . The award is quite elaborate . It takes into account nu-merous details . Arbitrator framed as many as 10 issues and then went on to examine each of the claims put forward by the parties with reference to the record before him . In the objections filed by AWHO it seeks remission of the award . The objections are though under Section 15 , 17 and 33 of the Act . In the course of arguments , it was submitted by Mr. Tiwari , learned counsel for the AWHO that the award be remitted back to the Arbitrator which would be under Section 16 of the Act , though in the prayer modi-fication of the award under Section 15 is sought . AWHO submitted that though it claimed certain amounts as ‘firm liability ‘ after the contract was cancelled and there were certain ‘anticipated expenses ‘ required to complete the contract . It was submitted that the Arbitrator treated even the firm liability as in the nature of elements of anticipated expenses and disallowed the same . It was submitted that on this account , the Arbitrator committed a mathematical error . It is not the case of the AWHO that the Arbitrator did not examine or did not take into account the claim put forward by the AWHO . It is not possible for us to re-appreciate the evidence produced before the Arbitrator and then ourselves coming to the conclusion whether a certain amount claimed was towards ‘firm liability ‘ or in the ‘nature of antici-pated expenses ‘ . Once the Arbitrator had held that the claim would be in the ‘nature of anticipated expenses ‘ , it is difficult for us to hold the same otherwise . It cannot be said that the award is not good on the face of it on that account . The objec-tions of AWHO have no force and IAs 21 to 24 are rejected .
6 . Under the terms of the contract GC&FL would be entitled to a total amount of Rs.54 ,95 ,271.72 as retention money from the total contract amount . The Arbitrator found that under the Contract , GC&FL executed work of the value of Rs.4 ,52 ,10 ,002/- and as such GC&FL would be entitled to retention money to the extent of 63.47% . Thus , from the retention money of Rs.54 ,95 ,271/- which GC&FL would be entitled to on completion of the contract , a sum of Rs.34 ,87 ,848.90 is now due to them being 63.47% of Rs.54 ,95 ,271.72. On completion of 50% of the work , GC&FL had already received Rs.30 ,00 ,000/- as retention money in three installments . Thus , GC&FL would be entitled to the balance amount of Rs.4 ,87 ,848.90 towards the retention money . The Arbitrator found that under claims 1 and 13 of GC&FL an amount of Rs.7 ,08 ,893.60 would be due to GC&FL From AWHO . This is how the Arbitrator arrived on this figure :
” The ultimate position is as follows :
RAR BILL 23 DEMAND : Rs.
1 . Value of work executed 4 ,50 ,44 ,002.35
2 . Value of extra works 1 ,66 ,000.00
3 . Total 4 ,52 ,10 ,002.35
4 . Value of materials lying at site 29 ,57 ,657.00
5 . Grand total 4 ,81 ,67 ,659.70
6 . Percentage of work done 63.47%
DEDUCTION Rs.
a) Retention Money 2 ,00 ,000
b) Cost of Schedule ” B “
materials supplied by
AWHO 1 ,69 ,37 ,615
c) Income Tax 11 ,52 ,990
d) Interest on Rs.18 lakhs
advance’ 6 ,26 ,117
e) Payment for RAR bills
upto Bill No.22 2 ,47 ,55 ,521
f) Advance of retention
money after 50%
work done 30 ,00 ,000
g) Advance made at site 12 ,74 ,372 4 ,79 ,46 ,615.00
Balance Receivable 2 ,21 ,044.70
h) Proportionate retention money
payable at 63.47% of Rs.54 ,95 ,271.72
less Rs.30 ,00 ,000/- already paid 4 ,87 ,848.90
Total Balance Receivable 7 ,08 ,893.60
——–
Thus , a sum of Rs.7 ,08 ,893.50 is allowed under Claim No.1 and 13. “
7 . The objection of GC&FL is that amount of Rs.30 ,00 ,000/- has been deducted twice by the Arbitrator which was a mistake appar-ent on the face of it and as such this Court should modify the award and grant a further amount of Rs.30 ,00 ,000/- to that alrea-dy awarded by the Arbitrator under claims 1 and 13 . We do not think that Mr. Thakur is right in his approach . GC&FL is enti-tled to Rs.4 ,87 ,848.90 towards balance of retention amount as an amount of Rs.30 ,00 ,000/- GC&FL had already received . GC&FL cannot be paid Rs.30 ,00 ,000/- twice over . In the claim made by GC&FL , it should have deducted Rs.30 ,00 ,000/- which it had alrea-dy received . As a matter of fact , the Arbitrator observed as under :-
” Claim No. 1 suffers from a serious flaw and the same can be rejected outright . On a perusal of the claim and the various items shown therein , it is seen that the petitioners have either inadvertently or deliberately omitted to deduct Rs.30 lakhs towards retention money obtained by them on three occa-sions for 50% of the work done . If this Rs.30 lakhs is deduct-ed from the claim made in Claim No.1 , the claim is reduced to a minus figure . This error , however , is seen corrected in the petitioners ‘ reply to the Respondents ‘ Claim No.1 . “
In fact , in the calculations aforesaid , under Item (h) , the Arbitrator could have said : ” Balance of the retention money payable – Rs.4 ,87 ,848.90 ” Retention money due to GC&FL is from the whole of the value of the contract . Total of retention money as arrived at by the Arbitrator is Rs.54 ,95 ,271.72 which is payable on completion of the contract by the AWHO . Since GC&FL executed only 63.47% of the value of the contract they became entitled to Rs.34 ,87 ,848.90 being 63.47% of Rs.54 ,95 ,271.72 . Having already received Rs.30 ,00 ,000/- GC&FL became entitled to balance amount of Rs.4 ,87 ,848.90 which the Arbitrator allowed them under the award .
8 . As far as the claim of interest is concerned , the award has already allowed the same and no objection thereto has been filed by AWHO or even by GC&FL on the claim due to AWHO under the award . IAs 17 to 20 of the GC&FL are rejected .
9 . IAs 13 to 16 filed by GC&FL seeking directions for modifica-tion of the Award and for grant of interest also stand dismissed .
10 . Accordingly the award dated September 9 , 1997 is made rule of the court and decree in terms thereof will be passed . Since both the parties have failed in their objections to the award , they shall bear their own costs .