Bharat Coking Coal Ltd. Vs. M/s. Annapurna Construction
Appeal: I.A. Nos. 1-2/2005 in Civil Appeal Nos. 5647-5648 of 1997
Petitioner: Bharat Coking Coal Ltd.
Respondent: M/s. Annapurna Construction
Apeal: I.A. Nos. 1-2/2005 in Civil Appeal Nos. 5647-5648 of 1997
Judges: S.B. Sinha & V.S. Sirpurkar, JJ.
Date of Judgment: Mar 05, 2008
Appearances:
Mr. Ajit Kumar Sinha and Mr. Aabhas Parimal, Advocates for the Appellant.
Mr. S.B. Upadhyay, Senior Advocate, Mr. Santosh Mishra, Mr. Paan Upadhyay, Mr. Shivmangal Sharma and Ms. Sharmila Upadhyay, Advocates, with him for the Respondent.
Mr. S.B. Upadhyay, Senior Advocate, Mr. Santosh Mishra, Mr. Paan Upadhyay, Mr. Shivmangal Sharma and Ms. Sharmila Upadhyay, Advocates, with him for the Respondent.
Head Note:
Arbitration
Arbitration Act, 1940
Sections 14, 17, 2(c) [Corresponding to Section 2(1)(e) of 1996 Act] – Jurisdiction to file Award – Award made earlier – Matter taken upto Supreme Court – Matter remitted back and fresh Arbitrator appointed – Parties agreed for Award to be made Rule of Court – Objection regarding jurisdiction of Supreme Court to entertain objections. Held that in this case since award was already made, the same now should be filed before court which has requisite jurisdiction i.e., the Civil Court. National Aluminium Co. Ltd.’s case relied and followed. Case law discussed.
Arbitration Act, 1940
Sections 14, 17, 2(c) [Corresponding to Section 2(1)(e) of 1996 Act] – Jurisdiction to file Award – Award made earlier – Matter taken upto Supreme Court – Matter remitted back and fresh Arbitrator appointed – Parties agreed for Award to be made Rule of Court – Objection regarding jurisdiction of Supreme Court to entertain objections. Held that in this case since award was already made, the same now should be filed before court which has requisite jurisdiction i.e., the Civil Court. National Aluminium Co. Ltd.’s case relied and followed. Case law discussed.
Held:
In the instant case, the matter came up before this Court whence an arbitrator had already been appointed and an award had been made. An arbitrator was appointed by this Court while setting aside the said award particularly in view of the fact that construction of the contract was in question. The court did not and could not retain any control over the proceedings of the arbitrator. (Para 12)
Thus, a distinction must be borne in mind in a case where this Court had no control over the proceedings and the case in which control of proceedings of the arbitrator had been retained. In the former case, having regard to the definition of the term ‘court’ as contained in Section 2(c) of the 1940 Act, award must be filed before a court which has the requisite jurisdiction thereover. (Para 13)
Ordinarily, although there may be cases to the contrary, the principle that the right of appeal should not be taken away, should be applied. There might be strong reason to deny the suitor a right of appeal. (Para 16)
By consent of the parties also, jurisdiction cannot be assumed by this Court. (Para
21)
For the foregoing reasons as also the binding precedents this Court has no jurisdiction to entertain these applications. The Registry, therefore, is directed to send the records to the Court of District Judge, Dhanbad who
in turn is directed to transfer the case to a court having appropriate jurisdiction. (Para
22)
Thus, a distinction must be borne in mind in a case where this Court had no control over the proceedings and the case in which control of proceedings of the arbitrator had been retained. In the former case, having regard to the definition of the term ‘court’ as contained in Section 2(c) of the 1940 Act, award must be filed before a court which has the requisite jurisdiction thereover. (Para 13)
Ordinarily, although there may be cases to the contrary, the principle that the right of appeal should not be taken away, should be applied. There might be strong reason to deny the suitor a right of appeal. (Para 16)
By consent of the parties also, jurisdiction cannot be assumed by this Court. (Para
21)
For the foregoing reasons as also the binding precedents this Court has no jurisdiction to entertain these applications. The Registry, therefore, is directed to send the records to the Court of District Judge, Dhanbad who
in turn is directed to transfer the case to a court having appropriate jurisdiction. (Para
22)
Cases Reffered:
1. Pandey and Co. Builders (P) Ltd. v. State of Bihar and Another [JT 2006 (10) SC 414] (Para 8)
2. Garhwal Mandal Vikas Nigam Ltd. v.M/s. Krishna Travel Agency [IA 1 and 2 in SLP (C) No. 18344 of 2004 dated 24.01.2007] (Para 19)
3. State of Goa v. Western Builders [JT 2006 (6) SC 125] (Para 15)
4. ITC Ltd. v. George Joseph Fernandes and Another [2005 (10) SCC 425] (Para 20)
5. Mcdermott International Inc. v. Burn Standard Co. Ltd. and Others [2005 (10) SCC 353] (Para 20)
6. National Aluminium Co. Ltd. v. Pressteel and Fabrications (P) Ltd. and Another [JT 2004 (5) SC 582] (relied and followed) (Para 14)
7. State of Maharashtra v. Indian Medical Association and Others [JT 2001 (10) SC 294] (Para 8)
8. M/s. Bharat Coking Coal Ltd. v. H.P. Biswas and Company [Civil Appeal No. 3504 of 1992] (Para 18)
9. M/s. Guru Nank Foundation v. M/s. Rattan Singh and Sons [1981 (4) SCC 634] (Para 11)
10. State of Madhya Pradesh v. M/s. Saith and Skelton (P) Ltd. [1972 (1) SCC 702] (Para 10.1)
2. Garhwal Mandal Vikas Nigam Ltd. v.M/s. Krishna Travel Agency [IA 1 and 2 in SLP (C) No. 18344 of 2004 dated 24.01.2007] (Para 19)
3. State of Goa v. Western Builders [JT 2006 (6) SC 125] (Para 15)
4. ITC Ltd. v. George Joseph Fernandes and Another [2005 (10) SCC 425] (Para 20)
5. Mcdermott International Inc. v. Burn Standard Co. Ltd. and Others [2005 (10) SCC 353] (Para 20)
6. National Aluminium Co. Ltd. v. Pressteel and Fabrications (P) Ltd. and Another [JT 2004 (5) SC 582] (relied and followed) (Para 14)
7. State of Maharashtra v. Indian Medical Association and Others [JT 2001 (10) SC 294] (Para 8)
8. M/s. Bharat Coking Coal Ltd. v. H.P. Biswas and Company [Civil Appeal No. 3504 of 1992] (Para 18)
9. M/s. Guru Nank Foundation v. M/s. Rattan Singh and Sons [1981 (4) SCC 634] (Para 11)
10. State of Madhya Pradesh v. M/s. Saith and Skelton (P) Ltd. [1972 (1) SCC 702] (Para 10.1)
JUDGEMENT:
S.B. Sinha, J.
1. Which would be the appropriate court for the purpose of filing of an award by the arbitrator is the question involved herein.
2. The said question arises in the following circumstances:
2.1 Respondent herein admittedly was a contractor of the appellant. Disputes and differences having arisen between the parties, the arbitration agreement was invoked. An arbitrator was appointed.
2.2 The parties hereto raised their claims and counter-claims before the arbitrator. He made an award of Rs.18,97,729.37 in favour of the respondent.
3. A question of law was raised when the matter ultimately came up before the court arising out of the proceedings for making the said award a rule of the court, and this Court in its judgment dated 29.08.2003 [since reported in JT 2003 (Suppl.1) SC 280], while setting aside the award, directed:
’40. However, as noticed hereinbefore, this case stands on a different footing, namely, that the arbitrator while passing the award in relation to some items failed and/or neglected to take into consideration the relevant clauses of the contract, nor did he take into consideration the relevant materials for the purpose of arriving at a correct fact. Such an order would amount to misdirection in law.
41. We are, therefore, of the opinion that the matter requires reconsideration. Having regard to the facts and circumstances of this case and particularly keeping in view the fact that the matter relates to pure interpretation of document which gives rise to question of law and in stead and in place of remitting the matter to the named arbitrator, we would direct that the disputes in relation to Claim Items 3, 7 and 11 be referred to the Hon’ble Mr Justice D.N. Prasad, a retired Judge of the Jharkhand High Court on such terms and conditions as may be mutually agreed upon by the parties. The learned arbitrator is requested to consider the desirability of making his award as expeditiously as possible keeping in view the fact that the matter has been pending for a long time.’
4. Before the learned arbitrator, three claims were raised by the respondent, viz., Claim Item Nos. 3, 7 and 11. Claim Item No. 3 related to extra items which has been rejected. Claim Item No. 7 related to loss of profit. Respondent raised a claim of Rs. 27,77,714/-; an award of Rs. 12,20,289/- was made. So far as Claim Item No. 11 is concerned, which related to the escalation of materials, an award of Rs. 90,005/- was made. It appears that before the arbitrator parties agreed that the award be filed before this Court.
4.1. However, an objection has been filed by the appellant wherein inter alia the jurisdiction of this Court to entertain the objection filed under the Arbitration Act, 1940 (for short ‘the 1940 Act’) has been questioned.
5. Indisputably, the 1940 Act will apply in this case.
6. Section 2(c) of the 1940 Act read as under:
‘2. In this Act, unless there is anything repugnant in the subject or context, –
*** *** ***
‘Court’ means a Civil Court having jurisdiction to decide the questions forming the subject-matter of the reference if the same had been the subject-matter of a suit, but does not except for the purpose of arbitration proceedings under Section 21 include a Small Cause Court;’
7. Although strictly, it is not necessary but we may also notice the change in the definition of the term ‘court’ brought in by the Parliament in Arbitration and Conciliation Act, 1996 as contained in Section 2(1)(e) therein which reads as under:
‘2. (1) In this Part, unless the context otherwise requires, –
*** *** ***
(e) ‘Court’ means the Principal Civil Court of Original Jurisdiction in a district, and includes the High Court in exercise of its ordinary original civil jurisdiction, having jurisdiction to decide the questions forming the subject-matter of the arbitration if the same had been the subject-matter of a suit, but does not include any civil court of a grade inferior to such Principal Civil Court, or any Court of Small Causes;’
8. It is now a trite law that whenever a term has been defined under a statute, the same should ordinarily be given effect to. There cannot, however, be any doubt whatsoever that the interpretation clause being prefaced by the words ‘unless there is anything repugnant in the subject and context’ may in given situations lead this Court to opine that the legislature intended a different meaning. [See State of Maharashtra v. Indian Medical Association and Others [JT 2001 (10) SC 294] and Pandey and Co. Builders (P) Ltd. v. State of Bihar and Another [JT 2006 (10) SC 414].
9. While determining such a question, the court ordinarily again must preserve the right of a party to prefer an appeal. A right of appeal is a valuable right and unless there exist cogent reasons, a litigant should not be deprived of the same. It is a statutory right.
10. With the aforementioned background, we may notice a few precedents operating in the field.
10.1. In State of Madhya Pradesh v. M/s. Saith and Skelton (P) Ltd. [1972 (1) SCC 702], apart from appointing the arbitrator, this Court extended the time for making the award. It was held that this Court would be entitled to entertain an application under Section 14(2) read with Section 30 of the 1940 Act stating:
’18. According to Mr Shroff the Award should have been filed, not in this Court, but in the Court of the Addl. District Judge, Mandsaur, as that is the Court which will have jurisdiction to entertain the suit regarding the subject-matter of the reference. We are not inclined to accept this contention of Mr Shroff. It should be noted that the opening words of Section 2 are ‘In this Act, unless there is anything repugnant in the subject or context’. Therefore the expression ‘Court’ will have to be understood as defined in Section 2(c) of the Act, only if there is nothing repugnant in the subject or context. It is in that light that the expression ‘Court’ occurring in Section 14(2) of the Act will have to be understood and interpreted. It was this Court that appointed Shri V.S. Desai, on January 29, 1971, by consent of parties as an arbitrator and to make his Award. It will be seen that no further directions were given in the said order which will indicate that this Court had not divested itself of its jurisdiction to deal with the Award or matters arising out of the Award. In fact the indications are to the contrary. The direction in the order, dated January 29, 1971, is that the arbitrator is ‘to make his Award’. Surely the law contemplates further steps to be taken after the Award has been made, and quite naturally the forum for taking the further action is only this Court. There was also direction to the effect that the parties are at liberty to apply for extension of time for making the Award. In the absence of any other court having been invested with such jurisdiction by the order, the only conclusion that is possible is that such a request must be made only to the court which passed that order, namely, this Court.’
It was furthermore observed:
’21. in Ct. A. Ct. Nachiappa Chettiar v. Ct. A. Ct. Subramaniam Chettiar the question arose whether the trial court had jurisdiction to refer the subject-matter of a suit to an arbitrator when the decree passed in the suit was pending appeal before the High Court. Based upon Section 21, it was urged before this Court that the reference made by the trial court, when the appeal was pending, and the award made in consequence of such reference, were both invalid as the trial court was not competent to make the order of reference. This Court rejected the said contention and after a reference to Sections 2(c) and 21 of the Act held that the expression ‘Court’ occurring in Section 21 includes also the appellate court, proceedings before which are a continuance of the suit. It was further held that the word ‘suit’ in Section 21 includes also appellate proceedings. In our opinion, applying the analogy of the above decision, the expression ‘Court’ occurring in Section 14(2) of the Act will have to be understood in the context in which it occurs. So understood, it follows that this Court is the Court under Section 14(2) where the arbitration Award could be validly filed.’
11. The said principle was reiterated in M/s. Guru Nank Foundation v. M/s. Rattan Singh and Sons [1981 (4) SCC 634] wherein it was opined:
’18…By the decision of this Court in the appeal the 2nd respondent was removed as arbitrator and the 3rd respondent was appointed as sole arbitrator. Indisputably, therefore, the arbitrator was appointed by this Court. The order appointing the 3rd respondent as arbitrator gave a further direction that the arbitrator shall enter upon the reference within 15 days from the date of the Order of the Court and he should try to dispose of the same as expeditiously as possible. The final Order was that the appeal was disposed of in terms hereinabove indicated. A contention that thereafter this Court was not in seisin of the matter was urged relying upon the fact that the appeal was disposed of by the Order of the Court and that there was no further proceeding before this Court. This contention has merely to be stated to be rejected, as will be presently pointed out. After the disposal of the appeal, CMP No. 896 of 1977 was presented to this Court for clarification and/or modification of the Order of the Court dated January 5, 1977. This Court by its Order dated February 10, 1977, gave further directions and a specific time-limit was fixed by this Court directing the 3rd respondent as arbitrator to conclude the proceedings within four months from the date of Order of the Court. Even with regard to the conduct of proceedings this Court directed that the 3rd respondent should proceed with the reference from the stage where it was left by the 2nd respondent and that not only that he may permit additional evidence to be led but he must consider the pleadings and evidence already placed before the previous arbitrator. This will indisputably show that this Court had complete control over the proceedings before the arbitrator.’
12. Both the aforementioned decisions, therefore, proceed on the basis that the court had complete control over the proceedings of the arbitrator. In the instant case, however, the matter came up before this Court whence an arbitrator had already been appointed and an award had been made. An arbitrator was appointed by this Court while setting aside the said award particularly in view of the fact that construction of the contract was in question. The court did not and could not retain any control over the proceedings of the arbitrator.
13. Thus, a distinction must be borne in mind in a case where this Court had no control over the proceedings and the case in which control of proceedings of the arbitrator had been retained. In the former case, having regard to the definition of the term ‘court’ as contained in Section 2(c) of the 1940 Act, award must be filed before a court which has the requisite jurisdiction thereover.
14. We may notice that such a view has been taken by this Court in National Aluminium Co. Ltd. v. Pressteel and Fabrications (P) Ltd. and Another [JT 2004 (5) SC 582] stating:
‘9…In regard to the forum before which the application for modification or setting aside the award is concerned, we find no difficulty in coming to the conclusion that in view of the provisions of Section 34 read with Section 2(e) of the 1996 Act it is not this Court which has the jurisdiction to entertain an application for modification of the award and it could only be the principal civil court of original jurisdiction as contemplated under Section 2(e) of the Act, therefore, in our opinion, this application is not maintainable before this Court.’
15. Yet again in State of Goa v. Western Builders [JT 2006 (6) SC 125], this Court opined:
’21. In National Aluminium Co. Ltd. v. Pressteel and Fabrications (P) Ltd. unilateral appointment of the arbitrator under the Arbitration Act, 1940 was challenged. This Court in the said appeal after hearing the parties appointed a sole arbitrator. Before the sole arbitrator both the parties by consent agreed that the proceedings should be governed by the provisions of the Arbitration and Conciliation Act, 1996. The arbitrator proceeded on that basis and gave a final award. That final award was challenged. The question arose whether the proceeding shall be governed by the 1940 Act or by the 1996 Act? And which is the appropriate court. The dispute prolonged for nearly 16 years. This Court dismissed the appeal and held that in the present case proceedings should go on under the provisions of the Act, 1996 though the dispute arose prior to coming into force of the Act, 1996, the appropriate forum for challenging the award under Section 34 was the Principal Civil Court of original jurisdiction as contemplated under Section 2(e) of the Act, 1996.’
16. Ordinarily, although there may be cases to the contrary, the principle that the right of appeal should not be taken away, should be applied. There might be strong reason to deny the suitor a right of appeal.
17. In Pandey and Co. Builders (P) Ltd. (supra), however, in the fact situation obtaining therein, this Court held :
’23. In this case, it is not necessary for us to go into the question as to whether sub-section (3) of Section 37 of the 1996 Act would debar an appeal from appellate order passed under sub-section (2) of Section 37 thereof. The consequences of the statutory embargo would ensue but then the question will have to be considered as and when occasion arises therefor. Sub-section (2) of Section 37 of the 1996 Act prescribes for an appeal to a court. We do not see any reason as to why having regard to its plain language, the definition of ‘court’ shall not be put into service. It may be true that the interpretation clause provides for ‘unless the context otherwise requires’. If application of the interpretation clause contained in Section 2 of the 1996 Act shall lead to anomalous and absurd results, one may not stick to the definition but we do not think that such a case has been made out.’
18. Reliance has also been placed by Mr. Ajit Kumar Sinha, learned counsel appearing on behalf of the appellant on an order of this Court dated 22.08.1997 in M/s. Bharat Coking Coal Ltd. v. H.P. Biswas and Company [Civil Appeal No. 3504 of 1992] wherein it was directed:
‘In this civil appeal an award has been filed by the Arbitrator appointed by this Court in a proceeding arising out of Section 8 of the Arbitration Act before the trial Court. However, as the appeal arises out of the proceeding under the aforesaid section before the trial court, the appointment of the arbitrator by this Court was in substitution of the earlier order passed by the Trial Court. Hence the appropriate court in which the award is to be filed will be the Court of First Sub-Judge, Dhanbad. Therefore, the Registry is directed to send the original award as well as the entire records to the First Sub-Judge, Dhanbad, Bihar. On receipt of copy of this Order, original award and the records by the trial court, notice will be issued to the parties concerned by the trial court and within 30 days of receipt of such notice objection, if any, under Section 30 of the Arbitration Act will be filed by the concerned objector. Thereafter the trial court will proceed further in accordance with law. The trial court shall decide the objections, if any, of the parties concerned to the request for making the award a rule of the court. The trial court will dispose of the proceedings at an early date preferably within a period of six months from today…’
19. A Similar opinion was rendered yet recently by a Bench of this Court in Garhwal Mandal Vikas Nigam Ltd. v. M/s. Krishna Travel Agency [IA 1 and 2 in SLP (C) No. 18344 of 2004 dated 24.01.2007] wherein it was held:
‘Apart from these four cases, which have been brought to our notice, the position of law is very clear that in case the argument of learned counsel is accepted, that would mean that in every case where this court passes an order, be it on appeal, from the order passed by the High Court under Section 11(6) of the Arbitration and Conciliation Act, 1996, this court will become a Principal Civil Court of original jurisdiction. If the argument is further taken to its logical conclusion that would mean that the parties will have to approach this Court by making an application under Section 34 i.e. for setting aside the award. The expression ‘Court’ used in Section 34 of the Act will also have to be understood ignoring the definition of ‘Court’ in the Act. There is another facet of the problem. The party will be deprived of the right to file an appeal under Section 37(i)(b) of the Arbitration and Conciliation Act. This means that a valuable right of appeal will be lost. Therefore, in the scheme of things, the submission of the learned counsel cannot be accepted…’
[See also the comments in ‘Arbitration, Conciliation and Mediation’, Second edition by Shri V.A. Mohta, page 82]
20. It is also not a case where this Court has exercised its jurisdiction under sub-section (6) of Section 11 of the Arbitration and Conciliation Act, 1996 as was done in Mcdermott International Inc. v. Burn Standard Co. Ltd. and Others [2005 (10) SCC 353]. A similar view has been taken in ITC Ltd. v. George Joseph Fernandes and Another [2005 (10) SCC 425].
21. As the question of jurisdiction of a Court is involved herein, we are of the opinion, by consent of the parties also, jurisdiction cannot be assumed by this Court.
22. We, therefore, for the foregoing reasons as also the binding precedents are of the opinion that this Court has no jurisdiction to entertain these applications. The Registry, therefore, is directed to send the records to the Court of District Judge, Dhanbad who in turn is directed to transfer the case to a court having appropriate jurisdiction. The court concerned is requested to dispose of the objection filed by the appellant herein as expeditiously as possible and not later than three months from the date of receipt of records.
23. The applications are disposed of with the aforementioned directions. No costs.
1. Which would be the appropriate court for the purpose of filing of an award by the arbitrator is the question involved herein.
2. The said question arises in the following circumstances:
2.1 Respondent herein admittedly was a contractor of the appellant. Disputes and differences having arisen between the parties, the arbitration agreement was invoked. An arbitrator was appointed.
2.2 The parties hereto raised their claims and counter-claims before the arbitrator. He made an award of Rs.18,97,729.37 in favour of the respondent.
3. A question of law was raised when the matter ultimately came up before the court arising out of the proceedings for making the said award a rule of the court, and this Court in its judgment dated 29.08.2003 [since reported in JT 2003 (Suppl.1) SC 280], while setting aside the award, directed:
’40. However, as noticed hereinbefore, this case stands on a different footing, namely, that the arbitrator while passing the award in relation to some items failed and/or neglected to take into consideration the relevant clauses of the contract, nor did he take into consideration the relevant materials for the purpose of arriving at a correct fact. Such an order would amount to misdirection in law.
41. We are, therefore, of the opinion that the matter requires reconsideration. Having regard to the facts and circumstances of this case and particularly keeping in view the fact that the matter relates to pure interpretation of document which gives rise to question of law and in stead and in place of remitting the matter to the named arbitrator, we would direct that the disputes in relation to Claim Items 3, 7 and 11 be referred to the Hon’ble Mr Justice D.N. Prasad, a retired Judge of the Jharkhand High Court on such terms and conditions as may be mutually agreed upon by the parties. The learned arbitrator is requested to consider the desirability of making his award as expeditiously as possible keeping in view the fact that the matter has been pending for a long time.’
4. Before the learned arbitrator, three claims were raised by the respondent, viz., Claim Item Nos. 3, 7 and 11. Claim Item No. 3 related to extra items which has been rejected. Claim Item No. 7 related to loss of profit. Respondent raised a claim of Rs. 27,77,714/-; an award of Rs. 12,20,289/- was made. So far as Claim Item No. 11 is concerned, which related to the escalation of materials, an award of Rs. 90,005/- was made. It appears that before the arbitrator parties agreed that the award be filed before this Court.
4.1. However, an objection has been filed by the appellant wherein inter alia the jurisdiction of this Court to entertain the objection filed under the Arbitration Act, 1940 (for short ‘the 1940 Act’) has been questioned.
5. Indisputably, the 1940 Act will apply in this case.
6. Section 2(c) of the 1940 Act read as under:
‘2. In this Act, unless there is anything repugnant in the subject or context, –
*** *** ***
‘Court’ means a Civil Court having jurisdiction to decide the questions forming the subject-matter of the reference if the same had been the subject-matter of a suit, but does not except for the purpose of arbitration proceedings under Section 21 include a Small Cause Court;’
7. Although strictly, it is not necessary but we may also notice the change in the definition of the term ‘court’ brought in by the Parliament in Arbitration and Conciliation Act, 1996 as contained in Section 2(1)(e) therein which reads as under:
‘2. (1) In this Part, unless the context otherwise requires, –
*** *** ***
(e) ‘Court’ means the Principal Civil Court of Original Jurisdiction in a district, and includes the High Court in exercise of its ordinary original civil jurisdiction, having jurisdiction to decide the questions forming the subject-matter of the arbitration if the same had been the subject-matter of a suit, but does not include any civil court of a grade inferior to such Principal Civil Court, or any Court of Small Causes;’
8. It is now a trite law that whenever a term has been defined under a statute, the same should ordinarily be given effect to. There cannot, however, be any doubt whatsoever that the interpretation clause being prefaced by the words ‘unless there is anything repugnant in the subject and context’ may in given situations lead this Court to opine that the legislature intended a different meaning. [See State of Maharashtra v. Indian Medical Association and Others [JT 2001 (10) SC 294] and Pandey and Co. Builders (P) Ltd. v. State of Bihar and Another [JT 2006 (10) SC 414].
9. While determining such a question, the court ordinarily again must preserve the right of a party to prefer an appeal. A right of appeal is a valuable right and unless there exist cogent reasons, a litigant should not be deprived of the same. It is a statutory right.
10. With the aforementioned background, we may notice a few precedents operating in the field.
10.1. In State of Madhya Pradesh v. M/s. Saith and Skelton (P) Ltd. [1972 (1) SCC 702], apart from appointing the arbitrator, this Court extended the time for making the award. It was held that this Court would be entitled to entertain an application under Section 14(2) read with Section 30 of the 1940 Act stating:
’18. According to Mr Shroff the Award should have been filed, not in this Court, but in the Court of the Addl. District Judge, Mandsaur, as that is the Court which will have jurisdiction to entertain the suit regarding the subject-matter of the reference. We are not inclined to accept this contention of Mr Shroff. It should be noted that the opening words of Section 2 are ‘In this Act, unless there is anything repugnant in the subject or context’. Therefore the expression ‘Court’ will have to be understood as defined in Section 2(c) of the Act, only if there is nothing repugnant in the subject or context. It is in that light that the expression ‘Court’ occurring in Section 14(2) of the Act will have to be understood and interpreted. It was this Court that appointed Shri V.S. Desai, on January 29, 1971, by consent of parties as an arbitrator and to make his Award. It will be seen that no further directions were given in the said order which will indicate that this Court had not divested itself of its jurisdiction to deal with the Award or matters arising out of the Award. In fact the indications are to the contrary. The direction in the order, dated January 29, 1971, is that the arbitrator is ‘to make his Award’. Surely the law contemplates further steps to be taken after the Award has been made, and quite naturally the forum for taking the further action is only this Court. There was also direction to the effect that the parties are at liberty to apply for extension of time for making the Award. In the absence of any other court having been invested with such jurisdiction by the order, the only conclusion that is possible is that such a request must be made only to the court which passed that order, namely, this Court.’
It was furthermore observed:
’21. in Ct. A. Ct. Nachiappa Chettiar v. Ct. A. Ct. Subramaniam Chettiar the question arose whether the trial court had jurisdiction to refer the subject-matter of a suit to an arbitrator when the decree passed in the suit was pending appeal before the High Court. Based upon Section 21, it was urged before this Court that the reference made by the trial court, when the appeal was pending, and the award made in consequence of such reference, were both invalid as the trial court was not competent to make the order of reference. This Court rejected the said contention and after a reference to Sections 2(c) and 21 of the Act held that the expression ‘Court’ occurring in Section 21 includes also the appellate court, proceedings before which are a continuance of the suit. It was further held that the word ‘suit’ in Section 21 includes also appellate proceedings. In our opinion, applying the analogy of the above decision, the expression ‘Court’ occurring in Section 14(2) of the Act will have to be understood in the context in which it occurs. So understood, it follows that this Court is the Court under Section 14(2) where the arbitration Award could be validly filed.’
11. The said principle was reiterated in M/s. Guru Nank Foundation v. M/s. Rattan Singh and Sons [1981 (4) SCC 634] wherein it was opined:
’18…By the decision of this Court in the appeal the 2nd respondent was removed as arbitrator and the 3rd respondent was appointed as sole arbitrator. Indisputably, therefore, the arbitrator was appointed by this Court. The order appointing the 3rd respondent as arbitrator gave a further direction that the arbitrator shall enter upon the reference within 15 days from the date of the Order of the Court and he should try to dispose of the same as expeditiously as possible. The final Order was that the appeal was disposed of in terms hereinabove indicated. A contention that thereafter this Court was not in seisin of the matter was urged relying upon the fact that the appeal was disposed of by the Order of the Court and that there was no further proceeding before this Court. This contention has merely to be stated to be rejected, as will be presently pointed out. After the disposal of the appeal, CMP No. 896 of 1977 was presented to this Court for clarification and/or modification of the Order of the Court dated January 5, 1977. This Court by its Order dated February 10, 1977, gave further directions and a specific time-limit was fixed by this Court directing the 3rd respondent as arbitrator to conclude the proceedings within four months from the date of Order of the Court. Even with regard to the conduct of proceedings this Court directed that the 3rd respondent should proceed with the reference from the stage where it was left by the 2nd respondent and that not only that he may permit additional evidence to be led but he must consider the pleadings and evidence already placed before the previous arbitrator. This will indisputably show that this Court had complete control over the proceedings before the arbitrator.’
12. Both the aforementioned decisions, therefore, proceed on the basis that the court had complete control over the proceedings of the arbitrator. In the instant case, however, the matter came up before this Court whence an arbitrator had already been appointed and an award had been made. An arbitrator was appointed by this Court while setting aside the said award particularly in view of the fact that construction of the contract was in question. The court did not and could not retain any control over the proceedings of the arbitrator.
13. Thus, a distinction must be borne in mind in a case where this Court had no control over the proceedings and the case in which control of proceedings of the arbitrator had been retained. In the former case, having regard to the definition of the term ‘court’ as contained in Section 2(c) of the 1940 Act, award must be filed before a court which has the requisite jurisdiction thereover.
14. We may notice that such a view has been taken by this Court in National Aluminium Co. Ltd. v. Pressteel and Fabrications (P) Ltd. and Another [JT 2004 (5) SC 582] stating:
‘9…In regard to the forum before which the application for modification or setting aside the award is concerned, we find no difficulty in coming to the conclusion that in view of the provisions of Section 34 read with Section 2(e) of the 1996 Act it is not this Court which has the jurisdiction to entertain an application for modification of the award and it could only be the principal civil court of original jurisdiction as contemplated under Section 2(e) of the Act, therefore, in our opinion, this application is not maintainable before this Court.’
15. Yet again in State of Goa v. Western Builders [JT 2006 (6) SC 125], this Court opined:
’21. In National Aluminium Co. Ltd. v. Pressteel and Fabrications (P) Ltd. unilateral appointment of the arbitrator under the Arbitration Act, 1940 was challenged. This Court in the said appeal after hearing the parties appointed a sole arbitrator. Before the sole arbitrator both the parties by consent agreed that the proceedings should be governed by the provisions of the Arbitration and Conciliation Act, 1996. The arbitrator proceeded on that basis and gave a final award. That final award was challenged. The question arose whether the proceeding shall be governed by the 1940 Act or by the 1996 Act? And which is the appropriate court. The dispute prolonged for nearly 16 years. This Court dismissed the appeal and held that in the present case proceedings should go on under the provisions of the Act, 1996 though the dispute arose prior to coming into force of the Act, 1996, the appropriate forum for challenging the award under Section 34 was the Principal Civil Court of original jurisdiction as contemplated under Section 2(e) of the Act, 1996.’
16. Ordinarily, although there may be cases to the contrary, the principle that the right of appeal should not be taken away, should be applied. There might be strong reason to deny the suitor a right of appeal.
17. In Pandey and Co. Builders (P) Ltd. (supra), however, in the fact situation obtaining therein, this Court held :
’23. In this case, it is not necessary for us to go into the question as to whether sub-section (3) of Section 37 of the 1996 Act would debar an appeal from appellate order passed under sub-section (2) of Section 37 thereof. The consequences of the statutory embargo would ensue but then the question will have to be considered as and when occasion arises therefor. Sub-section (2) of Section 37 of the 1996 Act prescribes for an appeal to a court. We do not see any reason as to why having regard to its plain language, the definition of ‘court’ shall not be put into service. It may be true that the interpretation clause provides for ‘unless the context otherwise requires’. If application of the interpretation clause contained in Section 2 of the 1996 Act shall lead to anomalous and absurd results, one may not stick to the definition but we do not think that such a case has been made out.’
18. Reliance has also been placed by Mr. Ajit Kumar Sinha, learned counsel appearing on behalf of the appellant on an order of this Court dated 22.08.1997 in M/s. Bharat Coking Coal Ltd. v. H.P. Biswas and Company [Civil Appeal No. 3504 of 1992] wherein it was directed:
‘In this civil appeal an award has been filed by the Arbitrator appointed by this Court in a proceeding arising out of Section 8 of the Arbitration Act before the trial Court. However, as the appeal arises out of the proceeding under the aforesaid section before the trial court, the appointment of the arbitrator by this Court was in substitution of the earlier order passed by the Trial Court. Hence the appropriate court in which the award is to be filed will be the Court of First Sub-Judge, Dhanbad. Therefore, the Registry is directed to send the original award as well as the entire records to the First Sub-Judge, Dhanbad, Bihar. On receipt of copy of this Order, original award and the records by the trial court, notice will be issued to the parties concerned by the trial court and within 30 days of receipt of such notice objection, if any, under Section 30 of the Arbitration Act will be filed by the concerned objector. Thereafter the trial court will proceed further in accordance with law. The trial court shall decide the objections, if any, of the parties concerned to the request for making the award a rule of the court. The trial court will dispose of the proceedings at an early date preferably within a period of six months from today…’
19. A Similar opinion was rendered yet recently by a Bench of this Court in Garhwal Mandal Vikas Nigam Ltd. v. M/s. Krishna Travel Agency [IA 1 and 2 in SLP (C) No. 18344 of 2004 dated 24.01.2007] wherein it was held:
‘Apart from these four cases, which have been brought to our notice, the position of law is very clear that in case the argument of learned counsel is accepted, that would mean that in every case where this court passes an order, be it on appeal, from the order passed by the High Court under Section 11(6) of the Arbitration and Conciliation Act, 1996, this court will become a Principal Civil Court of original jurisdiction. If the argument is further taken to its logical conclusion that would mean that the parties will have to approach this Court by making an application under Section 34 i.e. for setting aside the award. The expression ‘Court’ used in Section 34 of the Act will also have to be understood ignoring the definition of ‘Court’ in the Act. There is another facet of the problem. The party will be deprived of the right to file an appeal under Section 37(i)(b) of the Arbitration and Conciliation Act. This means that a valuable right of appeal will be lost. Therefore, in the scheme of things, the submission of the learned counsel cannot be accepted…’
[See also the comments in ‘Arbitration, Conciliation and Mediation’, Second edition by Shri V.A. Mohta, page 82]
20. It is also not a case where this Court has exercised its jurisdiction under sub-section (6) of Section 11 of the Arbitration and Conciliation Act, 1996 as was done in Mcdermott International Inc. v. Burn Standard Co. Ltd. and Others [2005 (10) SCC 353]. A similar view has been taken in ITC Ltd. v. George Joseph Fernandes and Another [2005 (10) SCC 425].
21. As the question of jurisdiction of a Court is involved herein, we are of the opinion, by consent of the parties also, jurisdiction cannot be assumed by this Court.
22. We, therefore, for the foregoing reasons as also the binding precedents are of the opinion that this Court has no jurisdiction to entertain these applications. The Registry, therefore, is directed to send the records to the Court of District Judge, Dhanbad who in turn is directed to transfer the case to a court having appropriate jurisdiction. The court concerned is requested to dispose of the objection filed by the appellant herein as expeditiously as possible and not later than three months from the date of receipt of records.
23. The applications are disposed of with the aforementioned directions. No costs.